.04 Selection of the Design-Builder.

A. Selection of a design-builder shall be conducted using the multi-step sealed bid procurement method as provided in COMAR 21.05.02.17 or the competitive sealed proposals procurement method as provided in COMAR 21.05.03.

B. The invitation for bids or request for proposals shall contain at a minimum:

(1) The minimum qualifications of the design-builder;

(2) Requirements for construction and design experience and experience in other design-build projects provided the requirements do not unduly restrict competition;

(3) The scope of work; and

(4) Responsibilities of the State and design-builder particularly in the areas of design defects and warranties.